The blockwork should be as accurate here as when above the DPC - otherwise the blockwork above DPC will not be accurate - it figures.
|
|
|
|
|
|
The outer leaf is left one block down from the DPC level and the cavity filled with a weak concrete mix to that level. Bitumonous paint will be applied before the blockwork is taken above DPC - this is further described at Block work to joist level |
|
|
The photo to the left shows the preparation below slab to support chimney breast - a lot of blocks laid flat. |
|
|
|
|
|
|
The outer leaf is left one block down from the DPC level and the cavity filled with a weak concrete mix to that level. Bitumonous paint will be applied before the blockwork is taken above DPC - this is further described at Block work to joist level |
|
|
The photo above shows the preparation below slab to support chimney breast - a lot of blocks laid flat. |